Previous Construction Page October 18, 2003 - The big pour
| 7:00am - The
first of 11 cement trucks roll in. The guys start moving cement. |
 |
| 9:00am -
Moving along, almost half way. |
 |
| 9:30am -
Diane Bettencourt, Dennis Mangan and John Pade take a break for a
photo as the cement is pumped in behind them. |
 |
| 10:00 - The
trucks keep coming... |
 |
| 11:00am -
Getting closer to the North wall |
 |
| 2:00pm - Final
finishing is almost done. |
 |
| 2:30pm - Lisa
gets to write in the nearly-set concrete. |
 |
| 3:30pm - 8 1/2
hours and 110 yards of concrete later, everyone enjoys lunch.
The entire floor is done and beautifully finished. |
 |
|
|
|